THE SAILBOAT RENOVATION
PURCHASING THE SAILBOAT
January, 2020

Purchase of a Sun Kiss 45 built in 1985,
in poor condition and taken out of the water in 2015.
DISMANTLING
& UNSTEPPING THE MAST
February - March, 2020

Stripping down the interior
of the sailboat.
Removal of the engine, mast, and rudder.
STRUCTURAL WORKS
April - May, 2020

Replacement and lamination
of damaged frames and stringers.
TRAVAUX PRÉPARATOIRES
DU CARÉNAGE
Juin - Août 2020

Stripping the hull.
Overhauling through-hull fittings
and repairing the rudder.
REPLACEMENT OF PORTHOLES
August - November, 2020

Refurbishment of fixed
and mobile portholes.
INTERIOR REFURBISHMENT
August, 2020 - September, 2021

Cutting and installation
of new interior partitions.
ELECTRICITY & WATER NETWORKS
September, 2021 - May, 2022

Renovation of the tanks.
Installation of new water
and electricity networks.
SAILS & RIGGING
February, 2022 - June, 2022

Rigging and installation of navigation instruments, running rigging,
and standing rigging.
HULL MAINTENANCE
January, 2022 - June, 2022

Continuation of hull cleaning
and antifouling application.
FLOORS
September, 2022
LAUNCHING THE SAILBOAT
November, 2022

Cutting and fitting of new floorboards.
Application of a protective oil.